AE Data Center Aggregation Project Milestone

Target

Data Center Services delivery model drafted 5/30/2013
Identify campus partner(s) to participate in pilot exercise 6/15/2013
Create a draft charter for a future-state “Campus Data Center Leadership Committee” (defining scope / purpose, required participant expertise & commitment, etc…) 6/25/2013
Develop “Data center assessment model” 8/13/2013
Proposed governance structure created and documented 8/27/2013
Draft a high-level, long-term “Roadmap for Campus Data Center Aggregation” 8/27/2013
Services delivery model completed 8/27/2013
Present observations & recommendations to Steering Committee September 2013
Run the pilot exercise 9/3/2013
Transition the approved model to the business owner for implementation September 2013